Spaghetti Bowl Xpress (SBX) Traffic Control Update Week of October 10

Spaghetti Bowl Xpress (SBX) Traffic Control Update Week of October 10

Traffic control and detour maps are available here. Construction operations are weather dependent and subject to change.

NEW Southbound I-580 Villanova Off-ramp Closure

I-580 southbound Villanova Drive intermittently closed overnight from 8pm to 6am from Sunday, October 10 to Friday, October 15 for paving operations.
Detour use Moana Lane. Airport traffic use direct access ramp.

I-580 Villanova Southband Offramp Closure Map

Reno Spaghetti Bowl Ramp Closures

Ramps will be CLOSED intermittently overnight from 8pm to 6am from Sunday, October 10 to Friday, October 15. Please use marked detour routes.

  • Eastbound I-80 to northbound US-395.
  • Eastbound I-80 to southbound I-580.

NOTE: Both ramps will be closed overnight Tuesday, Wednesday and Thursday (October 12, 13 and 14), with detour available (follow signage).

Overnight I-80 Lane Reductions

Overnight lane reductions on eastbound I-80 between Keystone Avenue and the Spaghetti Bowl from 8pm to 5am, Sunday, October 10 to Friday, October 15.

Overnight I-580 Lane Reductions

Overnight lane reductions on southbound I-580 between the Spaghetti Bowl and Mill Street from 8pm to 5am, Sunday, October 10 to Friday, October 15.

Southbound I-580 Second Street/Mill Street Off Ramps

Access to Second Street and/or Mill Street will be intermittently closed from the southbound I-580 Second Street/Mill Street off ramp overnight from 8pm to 6am from Sunday, October 10 to Friday, October 15.

Access to one route—either Second Street or Mill Street—will be available.

Kietzke Lane Closures

Kietzke Lane from Kuenzli Street to Galletti Way will be closed overnight from 8pm to 6am in both directions from Sunday, October 10 to Friday, October 15.

Eastbound I-80 Wells Avenue On Ramp Closure Through November

The Eastbound I-80 Wells Avenue on ramp is temporarily closed 24 hours/day, seven days/week until Friday, November 26. The closure is needed for the safety of drivers and workers while crews reconfigure the new eastbound I-80 to southbound I-580 ramp.

CONTACT US WITH ANY QUESTIONS

TEXT: 797979 with “SBX” for project updates via text
FACEBOOK: www.facebook.com/NevadaDOT
TWITTER: @nevadadotreno
HOTLINE: 775-636-4202
EMAIL: info@ndotspaghettibowl.com
WEBSITE: ndotspaghettibowl.com

Nighttime construction hours are approximately 8 pm to 6 am. Daytime construction hours are approximately 7 am to 5 pm. Drivers can expect reduced speeds through the work zone. All construction activities and times are subject to change and weather dependent.