Spaghetti Bowl Xpress (SBX) Traffic Control Update Week of August 28

Spaghetti Bowl Xpress (SBX) Traffic Control Update | Week of August 28, 2022

Traffic control and detour maps are available here. Construction operations are weather dependent and subject to change.

Reno Spaghetti Bowl Ramp Closures

The following ramps will be CLOSED intermittently overnight from 8pm to 6am on Sunday, August 28 to Friday, September 2. Please use marked detour routes.

  • Eastbound I-80 to northbound US 395.
  • Eastbound I-80 to southbound I-580.
  • Westbound I-80 to southbound I-580.

The northbound I-580 on ramp at Second Street is CLOSED 24-hours-a-day through Friday, September 2 as crews install gateway monuments and sign structure foundation.

Please follow marked detours and travel with caution through work areas.

Northbound and Southbound I-580 Lane Closures

Nightly lane reductions on northbound and southbound I-580 between the Spaghetti Bowl and Mill Street from 8pm to 6am from Monday, August 29 to Friday, September 2.

East Fourth Street Lane Reductions and Shifts

Day and night lane reductions and shifts take place on Fourth Street from Galletti Way to Sixth Street from Sunday, August 28 to Friday, September 2.

Note: Brief daytime traffic control delays to be expected.

Vassar Street Lane Reductions

Day and night lane reductions on Vassar Street under I-580 from Sunday, August 28 to Friday, September 2.

Market Street Shoulder Closure

Daytime shoulder closures on Market Street near Vassar Street from Sunday, August 28 to Friday, September 2.

Kietzke Lane Closures

Kietzke Lane from Kuenzli Street to Galletti Way will be CLOSED overnight from 8pm to 6am from Sunday, August 28 to Friday, September 2.

CONTACT US WITH ANY QUESTIONS

TEXT: 797979 with “SBX” for project updates via text
FACEBOOK: www.facebook.com/NevadaDOT
TWITTER: @nevadadotreno
HOTLINE: 775-636-4202
EMAIL: info@ndotspaghettibowl.com
WEBSITE: ndotspaghettibowl.com

Nighttime construction hours are approximately 8pm to 6am. Daytime construction hours are approximately 7am to 5pm. Drivers can expect reduced speeds through the work zone. All construction activities and times are subject to change and weather dependent.