Spaghetti Bowl Xpress (SBX) Project Update | December 16, 2022
NDOT’s Spaghetti Bowl Xpress Project is substantially complete! We appreciate the community’s patience during the last two years of construction.
Join us to learn more about the project and obtain the latest information on construction elements/activities and anticipated traffic control.
Washoe County is expected to see an increase of over 147,000 people over the next 20 years. The area is seeing a welcome influx of more commercial and industrial enterprises. The Nevada Department of Transportation (NDOT), in preparation for continued population growth, is improving portions along Interstate 80, Interstate 580, and U.S. 395, with particular attention to the I-80/I-580 Interchange, also known as the Spaghetti Bowl. In addition to these improvements, future traffic projections will be analyzed and infrastructure needs will be identified to take the Reno-Sparks area through the year 2040.
Spaghetti Bowl improvements include short, mid and long-range projects. Long-range projects may include the widening of the freeway and interchange ramps to accommodate increased traffic volumes.
NDOT’s Spaghetti Bowl Xpress Project is substantially complete! We appreciate the community’s patience during the last two years of construction.
The newly-widened eastbound Interstate 80 to southbound Interstate 580 ramp is now OPEN!
NEW Daytime lane and shoulder Spaghetti Bowl closures beginning Saturday, December 3.
NEW Nightly ramp closures on Oddie Boulevard to southbound US-395 on ramp from Monday, November 28 to Friday, December 2.
Crews will not be working over the Thanksgiving holiday, November 24–27. Construction will resume on Monday, November 28.
NEW Kietzke Lane daytime closure on November 17, NEW ramp closure at Wells Avenue from November 14–18, and NEW ramp closures between Keystone Ave. and the Spaghetti Bowl from November 14–18.
Continued Spaghetti Bowl construction and ramp and lane closures take place through November 11.
Continued Spaghetti Bowl construction and ramp and lane closures take place through November 5.
Construction will temporarily shut down for the Nevada Day holiday weekend on Thursday, October 27 at 5pm and resume on Sunday, October 30 at 8pm.
Continued Spaghetti Bowl ramp and lane closures through October 22.
Continued Spaghetti Bowl ramp and lane closures through October 17.
Continued Spaghetti Bowl ramp and lane closures through September 30.
Continued Spaghetti Bowl ramp and lane closures through September 30.
Continued Spaghetti Bowl ramp and lane closures through September 23.
Continued Spaghetti Bowl ramp and lane closures/reductions through September 17.
SBX traffic control will be reduced through the upcoming Labor Day weekend, and for the ongoing Burning Man and Rib Cook Off events.
Continued ramp closures from August 28 – September 2. Northbound I-580 on-ramp at Second Street closed 24/7 through September 2.
NEW Ramp closures from August 21–26 and Extended Closure Alert for the northbound I-580 on-ramp at Second Street.
NEW Ramp closures from August 14–17 and Extended Closure Alert for the northbound I-580 on-ramp at Second Street.
NEW Extended Closure Alert: The northbound I-580 on-ramp at Second Street will be closed 24/7 from Monday, August 8 to Friday, September 2 as crews install gateway monuments and sign structure foundation.
A new Second Street ramp opens soon, and ramp and lane closures continue as Spaghetti Bowl Xpress construction progresses.
A new Second Street ramp opens soon, and ramp and lane closures continue as Spaghetti Bowl Xpress construction progresses.
East Fourth Street overnight closures on July 18 and continued ramp and lane closures as Spaghetti Bowl Xpress construction continues.
NEW East Fourth Street overnight closures on July 14 and 18 as Spaghetti Bowl Xpress construction continues.
Construction will temporarily shut down on Friday, July 1 at 5pm until Tuesday, July 5 at 7am for the July 4 holiday.
Lane and ramp closures continue from June 12 through June 17 as construction crews work on Spaghetti Bowl Xpress improvements.
Traffic control and ramp closures are adjusted during the Reno Rodeo from June 16 to June 24.
Lane and ramp closures continue from June 12 through June 17 as construction crews work on Spaghetti Bowl Xpress improvements.
Lane and ramp closures continue as construction crews work on Spaghetti Bowl Xpress improvements.
The NDOT project team wishes the community a safe and happy Memorial Day. Construction will temporarily shut down Friday afternoon, May 27 and resume Tuesday morning, May 31.
NEW CLOSURE: East Fourth Street between Sixth Street and Galletti Way will be closed, 24-hours-a-day beginning at 8pm on Friday, May 20 through 6am on Monday, May 23.
Beginning Monday morning, May 16 at approximately 6 am, motorists will be shifted west and driving on the new southbound I-580 concrete lanes, offering a “Sneak Peek” of the final freeway configuration.
Motorists can expect the intermittent nightly ramp and lane closures from 8pm to 6am beginning Monday, May 9 through Monday morning, May 16.
Beginning Monday morning, May 16 at approximately 6am, motorists will be shifted west and driving on the new southbound I-580 concrete lanes, offering a “Sneak Peek” of the final freeway configuration.
COMING SOON: Motorists will be shifted west to the new southbound I-580 concrete lanes in May, offering a Sneak Peek of the final freeway configuration.
The NDOT SBX construction team recognized National Work Zone Awareness Week this week.
Northbound I-580 Mill Street on and off ramp intermittent overnight closures continue through Friday, April 15 for lighting and intelligent transportation system improvements.
NEW Northbound I-580 Mill Street on and off ramp intermittent overnight closures begin on Sunday, April 3 at 8pm.
Spaghetti Bowl Xpress improvements continue with overnight ramp and lane closures.
Since August 2021, the southbound I-580 exits to Second and Mill streets have been combined into one temporary exit. As of last week, Second and Mill streets are now accessed via new, separate exits.
Since August 2021, the southbound I-580 exits to Second and Mill streets have been combined into one temporary exit. Beginning Thursday, March 17 at 6 am, drivers wishing to exit at Second or Mill streets will use new, separate exits.
Ramp and lane closures continue through March 11 as crews continue work on Spaghetti Bowl improvements.
Spaghetti Bowl ramp closures continue. East Fourth Street between Sixth Street and Galletti Way is reduced to one travel lane, flagger-controlled, Monday through Friday, 24-hours-a-day through Friday, March 4.
Spaghetti Bowl ramp closures continue. East Fourth Street between Sixth Street and Galletti Way is reduced to one travel lane, flagger-controlled, Monday through Friday, 24-hours-a-day through Friday, February 25.
East Fourth Street between Sixth Street and Galletti Way will be reduced to one travel lane, flagger-controlled, Monday through Friday, 24-hours-a-day beginning Monday, February 14 through Friday, February 25.
Overnight ramp and lane closures continue to take place from 8pm on Monday, February 6, to 6am on Friday, February 11.
Overnight full closures of East Fourth Street from Galletti Way to Sixth Street continue to take place from 8pm on Monday, January 31 to 6am on Tuesday, February 1.
Nightly full closures of East Fourth Street from Galletti Way to Sixth Street begin, weeknights from 8pm to 6am from January 24 through February 1.
Nightly full closures of East Fourth Street from Galletti Way to Sixth Street are anticipated to take place week nights, January 24–31.
NDOT’s Reno Spaghetti Bowl Xpress improvements are on schedule, with more than 50 percent of overall construction completed while overcoming numerous weather restrictions and maintaining COVID precautions.
For easier holiday travel, no major SBX lane or ramp closures will take place from December 23, 2021 to January 3, 2022. Have a safe holiday!
Spaghetti Bowl construction continues with intermittent night ramp and lane closures through December 18.
Construction operations will continue during the week of December 5 with work primarily taking place on northbound I-580.
Continuing lane and ramp closures take place near the Spaghetti Bowl and will pause during the Thanksgiving Holiday weekend, resuming on Monday, November 29.
Drivers should anticipate intermittent overnight lane and ramp closures on northbound I-580 between Meadowood Mall Way and Mill Street next week.
The construction closure of the eastbound I-80 Wells Avenue on ramp was completed early and the Wells Avenue on ramp to eastbound I-80 is OPEN.
Crews will continue making repairs to surface cracking and potholes on I-580 between Mill Street and Moana Lane.
Next week crews will begin repairs to surface cracking and potholes on I-580 between Mill Street and Moana Lane.
Ramps will be CLOSED intermittently overnight from 8pm to 6am from Sunday, October 17 to Friday, October 22.
Drivers can expect the following traffic control during the week of October 10.
Drivers can expect the following traffic control during the week of October 3.
Drivers can expect the following traffic control during the week of September 19.
Drivers can expect the following traffic control during the week of September 19.
Drivers can expect the following traffic control during the week of September 12.
Drivers can expect the following traffic control during the week of September 5.
Drivers can expect the following traffic control during the week of August 29.
Spaghetti Bowl Xpress (SBX) Traffic Control Update Week of August 22
Spaghetti Bowl Xpress (SBX) Traffic Control Update Week of August 15
Spaghetti Bowl Xpress (SBX) Traffic Control Update Week of August 8
Spaghetti Bowl Xpress (SBX) Traffic Control Update Week of August 1
Spaghetti Bowl Xpress (SBX) Traffic Control Update Week of July 25
Drivers can expect the following traffic control during the week of July 18.
Drivers can expect the following traffic control during the week of July 11.
For easier 4th of July holiday travel, there will be no closures between 8 pm Friday, July 2 and 6 am Tuesday, July 6. Traffic control and detour maps are available here. Construction operations are weather dependent and subject to change.
“The Wildest, Richest Rodeo in the West” began on Wednesday, June 16 and will continue through Saturday night, June 26.
“The Wildest, Richest Rodeo in the West” began on Wednesday, June 16 and will continue through Saturday night, June 26.
Ramps will be CLOSED intermittently overnight from 9 pm to 6 am on Sunday, June 13 to Friday, June 18. Please use marked detour routes.
The Nevada Department of Transportation is announcing lane and ramp closures for the week of June 6 as part of continuing Reno Spaghetti Bowl improvements.
The Nevada Department of Transportation is announcing an extended closure of the Mill Street to southbound I-580 on ramp beginning Sunday, June 6 for approximately two weeks as part of continuing spaghetti bowl improvements.
Drivers can expect the following traffic control during the week of May 23. Traffic control and detour maps are available here.
Drivers can expect the following traffic control during the week of May 23. Traffic control and detour maps are available here.
Drivers can expect the following traffic control during the week of May 16.
The Nevada Department of Transportation is announcing overnight lane and ramp closures for the week of May 9 as part of continuing Reno Spaghetti Bowl improvements.
Ramps will be CLOSED intermittently overnight from 9 pm to 6 am on Sunday, May 9 to Friday, May 14. Please use marked detour routes.
Ramps will be CLOSED intermittently overnight from 9 pm to 6 am on Sunday, May 9 to Friday, May 14. Please use marked detour routes.
This week is National Work Zone Awareness Week, a week to remind motorists to drive safely in road work zones. With major highway improvement projects
With major highway improvement projects across the region, the Nevada Department of Transportation and Nevada Highway Patrol are reminding motorists to drive safely in road work zones, including during National Work Zone Awareness Week held April 26-30.
Drivers can expect the following traffic control during the week of April 18.
Drivers can expect the following traffic control during the week of April 18.
Drivers can expect the following traffic control during the week of April 18.
Drivers can expect the following traffic control during the week of April 18.
Drivers can expect the following traffic control during the week of April 11.
Drivers can expect the following traffic control during the week of April 4. Traffic control and detour maps are available here. Construction operations are weather dependent and subject to change.
Drivers will continue to see new interstate traffic configurations through spring of 2022. Known as the “Big Squeeze,” these lane and merge changes will “squeeze” traffic lanes through the spaghetti bowl as ramp and bridge improvements are made.
Drivers will continue to see new interstate traffic configurations through spring of 2022. Known as the “Big Squeeze,” these lane and merge changes will “squeeze” traffic lanes through the spaghetti bowl as ramp and bridge improvements are made.
Drivers will see new interstate traffic configurations beginning this week through spring of 2022. Known as the “Big Squeeze,” these new lane and merge changes will “squeeze” traffic lanes through the spaghetti bowl as ramp and bridge improvements are made.
MAJOR TRAFFIC CHANGE KNOWN AS “BIG SQUEEZE” BEGINS NEXT WEEK AS PART OF RENO SPAGHETTI BOWL XPRESS CONSTRUCTION
Second Street overnight ramp closures beginning Jan. 31 as part of continuing spaghetti bowl improvements. The following closures will take place as new ramp alignments are constructed as part of spaghetti bowl renovations.
The Nevada Department of Transportation is announcing weekend-long closures of Mill and Second streets underneath Interstate 580 beginning Jan. 22 as part of continuing Spaghetti Bowl improvements.
Read the Transport Topics article on the Reno Spaghetti Bowl Project
Reno spaghetti bowl ramp closures will take place in early January as construction progresses on the Nevada Department of Transportation’s Spaghetti Bowl Xpress project.
Reno spaghetti bowl ramp closures will take place in early January as construction progresses on the Nevada Department of Transportation’s Spaghetti Bowl Xpress project.
The Nevada Department of Transportation is announcing the next round of Reno spaghetti bowl ramp closures as part of the continuing Spaghetti Bowl Xpress project.
NDOT TO HOST VIRTUAL PUBLIC MEETING TO PROVIDE SPAGHETTI BOWL CONSTRUCTION UPDATES
Overnight spaghetti bowl ramp closures and Mill Street lane reductions will take place in October and November as construction progresses on the Nevada Department of Transportation’s Spaghetti Bowl Xpress project in Reno.
New traffic shifts and lane closures will begin Oct. 7 on northbound Interstate 580 between Mill Street and the Reno spaghetti bowl as construction progresses on the Nevada Department of Transportation’s Spaghetti Bowl Xpress project.
On behalf of the entire NDOT Spaghetti Bowl Project team, thank you for your support and patience as we launch construction of Phase 1, Spaghetti Bowl Xpress (SBX)! The launch of the project is the start of a safer and smoother interstate for our entire community and state.
On behalf of the entire NDOT Spaghetti Bowl Project team, thank you for your support and patience as we launch construction of Phase 1, Spaghetti Bowl Xpress (SBX)! The launch of the project is the start of a safer and smoother interstate for our entire community and state.
NDOT has launched construction of the Spaghetti Bowl Xpress project as crews prepare to remove and replace aging concrete on I-580 northbound between Mill Street and the Spaghetti Bowl. On northbound I-580 between Mill Street and the Spaghetti Bowl, you will see a football-shaped work zone separating traffic on either side for worker and driver safety.
Beginning, Sunday, August 23 drivers can expect additional nighttime lane reductions from 9 pm to 6 am on I-580 northbound between Mill Street and the spaghetti bowl. Speed limits are reduced and minor delays are anticipated.
Nevada Department of Transportation Launches Reno Spaghetti Bowl Project With Northbound I-580 Lane Closures
Safety is our top priority. The project team participates in daily safety meetings to review upcoming operations and coordinate activities.
Spaghetti Bowl Express (SBX) project design is in process.
Drivers will see periodic single lane closures on local roads near Interstate 580
Drivers will see temporary interstate shoulder and single lane closures
In November 2019 the Nevada Department of Transportation Board of Directors approved an unsolicited proposal to design and build SBX. A design build contract was approved in December 2019 with Ames Q&D Constructors, continuing momentum on these vital safety and capacity improvements. Key Preliminary Dates...
Safety, Congestion and Community Improvements Add a lane to eastbound exit from I-80 to I-580/U.S. 395 southbound. Add lanes and shoulders on I-580 southbound from I-80 to Vassar Street. Restripe Wells Avenue to I-80 eastbound on-ramp increasing lanes to I-580 southbound. Separate ramps for access...
This early action project, Spaghetti Bowl Xpress, serves as phase one of the Nevada Department of Transportation’s (NDOT’s) Spaghetti Bowl Project, and addresses the areas most critical for safety within the Spaghetti Bowl system-to-system interchange. With the proposed Spaghetti Bowl Xpress improvements shared below, eastbound I-80 backups approaching the exit to I-580/U.S. 395 should be greatly reduced or eliminated, and southbound I-580/U.S. 395 backups at the Spaghetti Bowl should be eliminated. Overall, freeway safety in general should improve.
Please note: Phase 1 will not be relocating any homes.
Updated SBX Schedule Coming Soon.